adf88 opened the ticket and wrote:
When adding new road type to an existing bridge or tunnel, the costs is halved. Steps to reproduce: Build a road bridge Add tram tracks to the bridge, note the cost Build (somewhere else) a tram track as long as the bridge, note the cost The second cost as twice big as the first one. Fix patch attached:
When adding new road type to an existing bridge or tunnel, the costs is halved.
Steps to reproduce:
Fix patch attached:
Attachments
Reported version: Version? Operating system: All
The text was updated successfully, but these errors were encountered:
Rubidium closed the ticket.
Reason for closing: Fixed
In r22699. Thanks for the fix.
Sorry, something went wrong.
No branches or pull requests
adf88 opened the ticket and wrote:
Attachments
Reported version: Version?
Operating system: All
This issue was imported from FlySpray: https://bugs.openttd.org/task/4681
The text was updated successfully, but these errors were encountered: